Tearing down and rebuilding a house in Los Altos (2026): lot rules, design review, demolition permit, timeline and cost

By Eric Sun · CSLB #1146788 · Updated

Short answer

In Los Altos you first check what the R1-10 lot allows (35% floor area, 27 ft and two stories, no second story once coverage passes 30%), get Zoning Administrator design review if the new house is two stories, final a demolition permit before the building permit can issue, clear plan check, then build within the city’s 7:00 a.m. to 5:30 p.m. weekday hours [1],[2],[5],[8]. Published Peninsula builder figures run roughly $400 to $1,200+ per sq ft and 18 to 30 months from design to move-in [9],[10],[11].

Step 1: What the lot allows

Most Los Altos houses sit in the R1-10 single-family district. The minimum site is 10,000 sq ft (11,000 sq ft on a corner, 15,000 sq ft on a flag lot) [1]. Floor area is capped at 35% of a net lot up to 11,000 sq ft; larger lots get 3,850 sq ft plus 10% of the area above 11,000 sq ft [1]. Height is 27 ft and two stories, but two rules cut that back: a flag lot is limited to one story and 20 ft, and any lot whose coverage exceeds 30% may not have a two-story structure and drops to a 20 ft limit [1]. A basement does not count as a story [1].

Setbacks are 25 ft front, 25 ft rear, 10 ft on interior sides for the first story and 17.5 ft for the second, and 20 ft on the street side of a corner lot [1]. On lots 70 ft or wider a daylight plane starts 11 ft up at each side property line and rises at 25 degrees, which is what shapes the upper floor [1]. Run these numbers before paying for design: the difference between a one-story and a two-story answer changes the approval path in the next step.

Step 2: Design review

Los Altos tiers its single-family design review by what you are building. A new one-story house under 20 ft gets administrative review by staff. A new two-story house, or a one-story converted to two, must be approved by the Zoning Administrator at a noticed public meeting before a building permit can be issued [2]. That structure comes from Ordinance 2025-534, adopted in July 2025 [2]. The FY2026-27 fee is $3,637.50 for administrative review of work over 150 sq ft and $6,726.61 for Zoning Administrator review [4].

Design review and the demolition permit run on separate tracks, but Planning signs off on both: every demolition, every tree protection plan and every tree removal needs Planning Division approval [5].

Step 3: Protected trees

Any tree 12 in. or more in diameter measured 48 in. above grade is protected, as is any native species at 10 in., any heritage tree, and any tree a previous approval required to be kept [3]. Removing one needs a permit; the FY2026-27 fee is $314.57 for the first tree [4]. Approved removals are generally replaced one for one with at least a 24-inch box tree [3]. The demolition application itself must include plans and photos showing tree protection already in place [5], so the arborist work comes before the wrecking crew, not after.

Step 4: The demolition permit

A demolition permit is required wherever any building, structure or pool is to be taken down, and it must be finaled before the building permit for the new house can be issued [5]. The city’s checklist is specific. Gas and electric service must be terminated at the main, confirmed by a disconnect letter from the utility; water service to the structure is disconnected (the property’s service line may stay); the sewer line is capped with an approved fitting and inspected by Engineering; and a BAAQMD “J number” letter is obtained for the air district [5]. Single-family demolitions are exempt from the PCB screening that applies to larger buildings [5].

  • Residential demolition application, plus a demolition site plan and a construction best-management-practices sheet [5]
  • Plans and photos of tree protection in place; two copies of a site plan showing every structure and tree to be removed, for Planning approval [5]
  • Utility disconnect letter (gas and electric), water disconnect, sewer cap inspected by Engineering, BAAQMD J number letter [5]
  • All demolition material goes to a city-approved recycling facility; weight tickets are submitted before the demolition final [5]
  • Submit the complete package to bldpermit@losaltosca.gov and allow 48 to 72 hours for processing [5]

Step 5: Building permit and plan check

Los Altos takes building permit submittals by email only and does not accept paper plans [7]. The city says a submittal is processed within 2 to 4 business days; that is the intake check, not the full review, and plan review does not begin until the plan check fees are paid in full [6],[7]. Fees are tiered by project valuation, and for FY2026-27 the valuation of any residential or commercial construction is set at no less than $591.39 per sq ft [4]. A 4,000 sq ft house is therefore valued at about $2.37 million for fee purposes, whatever your contract says. Once issued, a permit expires if work has not started or had a signed inspection within 365 days [7].

Step 6: Construction hours and neighbors

In single-family zones, construction tools and equipment may not run on weekdays before 7:00 a.m. or after 5:30 p.m., on Saturdays before 9:00 a.m. or after 3:00 p.m., or at any time on Sundays and city-observed holidays [8]. The same hours cover deliveries, worker arrival, start-up and shut-down on the site [8]. A rebuild in a built-out neighborhood lives or dies on this: the crew that shows up at 6:30 is the one the neighbors report.

Timeline at a glance

Fixed periods come from city documents; durations are published Peninsula builder estimates and vary by project
PhaseFixed by city rulesTypical duration (public estimates)
Design and engineeringNone3 to 5 months [10]
Design review (two-story)Zoning Administrator approval at a noticed public meeting before the building permit [2]No public duration found
Demolition permitProcessing 48 to 72 hours once complete; must be finaled before the building permit [5]Utility disconnects and the BAAQMD letter set the pace
Building permit plan checkIntake within 2 to 4 business days; review starts after fees are paid [6],[7]2 to 4 months [10]
ConstructionWeekdays 7:00 a.m. to 5:30 p.m., Saturdays 9:00 a.m. to 3:00 p.m. [8]10 to 16 months [10]; 14 to 24 months for luxury homes in nearby Menlo Park [11]
Total, design to move-inPermit expires after 365 days without a start or inspection [7]18 to 30 months [10]

What it costs: public ranges

No city publishes construction costs, and no builder we could find publishes Los Altos-specific numbers, so the figures below are what firms publish for neighboring Palo Alto and Menlo Park. Lot sizes, hillside sites and finish levels move the price more than the city line does. Treat them as ranges, not a quote.

Published cost ranges for custom homes next door to Los Altos (construction only, land excluded)
ItemPublished rangeSource
Standard to mid-range custom, Palo Alto$400 to $550 per sq ft[9]
High-end custom, Palo Alto$800 to $1,200+ per sq ft[9]
Luxury custom, Menlo Park$600 to $1,200+ per sq ft[11]
Demolition and site work$30,000 to $80,000[9]
Architecture and engineering8% to 12% of construction[9]
City permit valuation floor (sets fees, not cost)$591.39 per sq ft[4]

Rules and fees change every July with the city’s fee schedule and whenever the council amends the zoning code. Check the linked documents before relying on any figure here.

Common questions

Can I rebuild a two-story house on my Los Altos lot?
Only if the lot is not a flag lot and the new house keeps lot coverage at 30% or below; above 30% the R1-10 district allows one story and 20 ft [1]. A two-story house also needs Zoning Administrator design review at a public meeting before the building permit [2].
Do I need a separate demolition permit in Los Altos?
Yes. Any demolition of a building, structure or pool needs a demolition permit with utility disconnect letters, a BAAQMD J number, tree protection in place and Planning approval, and it must be finaled before the building permit for the new house is issued [5].
What hours can my contractor work in Los Altos?
In single-family zones: weekdays 7:00 a.m. to 5:30 p.m. and Saturdays 9:00 a.m. to 3:00 p.m.; nothing on Sundays or city-observed holidays. Deliveries and crew arrival count too [8].
How are Los Altos building permit fees calculated?
From project valuation, which for FY2026-27 is set at no less than $591.39 per sq ft of construction; plan review starts only after the plan check fees are paid in full [4],[6].

Sources

  1. [1] Los Altos Municipal Code Chapter 14.06 — R1-10 Single-Family District (Checked 2026-10-14)
  2. [2] Los Altos Municipal Code Chapter 14.77 — Design Review (Checked 2026-10-14)
  3. [3] Los Altos Municipal Code Chapter 11.08 — Tree Protection Regulations (Checked 2026-10-14)
  4. [4] City of Los Altos — Fee Schedule FY2026-27 (Checked 2026-10-14)
  5. [5] City of Los Altos — Demolition Permit Requirements & Instructions (Checked 2026-10-14)
  6. [6] City of Los Altos — New Single-Family Residence Plan Check Submittal Requirements (Checked 2026-10-14)
  7. [7] City of Los Altos — Building Division (Checked 2026-10-14)
  8. [8] Los Altos Municipal Code 6.16.070 — Noise Control, Prohibited Acts (construction hours) (Checked 2026-10-14)
  9. [9] Custom Home Design and Build — Custom Home Cost Palo Alto 2026 (Checked 2026-10-14)
  10. [10] Custom Home Design and Build — Building a Custom Home in Palo Alto 2026 (Checked 2026-10-14)
  11. [11] Ritz Builders — Luxury Custom Home Builder in Menlo Park, CA (Checked 2026-10-14)

Published

Find out what your lot can support

Tell us the address and what you have in mind, and we will run a free feasibility assessment: how much you can build, roughly how long it takes and what it is likely to cost. Or start by sketching your home in the browser.